A500 Etruria Widening – Open three months early
A500_Etruria_Stoke_On_Trent_Aerial_2

About the project

  • Network open three months early
  • £758k saved on piling method
  • 600 lorry movements saved
  • 100% waste reused or recycled

Stoke-on-Trent is growing and the A500 provides a strategic link connecting the city with the M6, local housing and the Etruria Valley Development. To ease congestion and improve safety between Porthill and Wolstanton junctions, a £17.5m scheme was proposed to widen this section of the A500 from two lanes to three in each direction. The extra lane would allow local traffic to hop between junctions avoiding the main flow